Permit numbers: LA County Public Works, EPIC-LA Fire Recovery Cases, pulled November 8, 2026 (data through November 5, 2026).
Twenty-two months after the Eaton Fire tore through Altadena on January 7, 2025, the rebuild is no longer a question of “if.” It’s a question of paperwork, pace, and plywood.
LA County has now issued 3,253 building permits for new single-family homes, ADUs and multi-family buildings in the Eaton Fire area. Crews are working on 1,873 properties. And 224 properties have a finished home or ADU on them.
Here’s how a rebuild moves through the system, and what the County’s own data says about where things stand.
First, who’s in charge
Altadena isn’t part of the City of Los Angeles or Pasadena. It’s unincorporated LA County, so rebuild permits go through the County, not LADBS. Applications run through EPIC-LA, the County’s online permitting portal, or in person at a County One-Stop Permit Center.
Four County departments review a rebuild: Regional Planning (zoning), Public Works Building & Safety (plans and permits), Fire, and Public Health.
The rebuild, step by step
According to the County’s like-for-like rebuild guide, every project follows the same four steps:
- Clear the lot. The U.S. EPA removed household hazardous waste first (Phase 1). Then owners either let the Army Corps of Engineers clear debris for free or hired an approved contractor (Phase 2). Owners can submit plans before cleanup is done, but the County won’t issue a permit until both phases are finished.
- Get the permit. Planning, Building & Safety, Fire and Public Health all have to sign off.
- Build and inspect. Owners schedule County inspections at set milestones.
- Move in. A Certificate of Occupancy from the County closes it out.
“Like-for-like” is the fast lane
The biggest fork in the road is whether a rebuild counts as like-for-like. That means the same size, same spot and same use as what burned. Per LA County Planning, owners get some wiggle room: floor area, height or footprint can grow by 10% or 200 square feet, whichever is greater.
Like-for-like rebuilds don’t have to meet current zoning rules, but they do have to meet current building, fire and health codes. The County says these reviews move faster.
Go bigger and you’re a non-like-for-like project. That means full zoning standards, including the Altadena Community Standards District, a 20-foot minimum front setback, and consistency with the West San Gabriel Valley Area Plan.
Two more things that trip people up: building inside the protected zone of an oak or other native tree needs a tree permit unless a legal structure was already there, and owners can put an RV or manufactured home on the lot as temporary housing while they rebuild.
Skipping the plan-check line
In May 2025 the County launched a self-certification pilot. Pre-registered California architects and engineers can certify that plans for a replacement home, ADU or accessory structure meet the County building code, skipping a full plan check. At least 20% of self-certified plans get randomly audited, and Planning, Fire and Public Health still have to approve. The County also offers pre-approved standard plans.
Where it stands: by the numbers
The funnel tells the story. 2,395 properties have a residential building permit. 1,873 of them are under construction. 224 are done.
Earlier in the pipeline, the County has logged 3,857 rebuild applications in the Eaton Fire area, and 3,643 have cleared zoning review.
The permit rush peaked in March
The first rebuild permits trickled out in spring 2025: 4 in April, 12 in May. By fall the pace picked up, and 2025 ended with 848 permits.
Then 2026 took off. January through October brought 2,363 permits, with a peak of 313 in March. Since July (279), the monthly count has eased each month: 198 in August, 185 in September, 174 in October.
Slowing permits don’t mean slowing work. More of the activity is now on job sites rather than at the permit counter, with 1,873 properties in construction.
ADUs are a big part of the rebuild
Of the 3,253 permits since the fire, 2,275 are single-family homes, 974 are ADUs and 4 are multi-family buildings. That’s roughly three ADU permits for every seven house permits. Plenty of Altadena owners are putting back more than one unit.
The money is real too. Those 3,253 permits carry $1.22 billion in declared project value. The median single-family rebuild permit lists $411,000, and the median ADU $112,250.
What it means if you work in Altadena
- Framing, roofing, windows, electrical and plumbing: 1,873 properties under construction means trades are needed now, all at once, in one small area.
- Finish trades (paint, tile, cabinets, flooring, landscaping): just 224 properties are finished. The big wave of finish work is still ahead.
- Everyone: these are County permits and County inspections, under current building and fire codes. Know the County’s process before you bid.