The Palisades Is Rebuilding. Here’s How It Works, and Where It Stands

By November 8th, 2026No Comments

Permit numbers: City of Los Angeles Department of Building and Safety (LADBS), permits and inspections on data.lacity.org, pulled November 8, 2026 (permits issued through October 30, 2026).

Twenty-two months after the Palisades Fire, the neighborhood is loud again. Not sirens this time. Concrete trucks and nail guns.

Since the fire, LADBS has issued 4,331 permits tagged as 2025 fire rebuilds in the Brentwood-Pacific Palisades area. 1,357 of them are for brand-new homes. 1,041 of those homes have started construction. And 59 are finished, with a Certificate of Occupancy in hand.

Here’s how a rebuild moves through City Hall, and what the City’s own data says about the pace.

First, who’s in charge

Most of the burn area is inside the City of Los Angeles, so rebuild permits go through LADBS and City Planning. That’s the big difference from Altadena, where LA County runs the show.

Not all of the burn zone is City land, though. Parts of the fire area are in the City of Malibu or unincorporated LA County, and those owners pull permits from Malibu or the County. Those properties aren’t in any of the numbers below.

The rebuild, step by step

  1. Clear the lot. Per the LADBS EO 1 Implementation Guidelines, LADBS needs paperwork from LA County Public Works showing the site is cleaned up and free of hazardous materials before it will issue a permit.
  2. Pick a lane. Like-for-like (EO 1), bigger single-family in the Coastal Zone (EO 8), or the regular process. More on that below.
  3. Submit plans. Online through ePlan, or walk in at the One-Stop Rebuilding Center at 1828 Sawtelle Blvd in West LA. Fire rebuilds get expedited plan review either way.
  4. Build and inspect. LADBS says rebuild inspections happen within two business days of a request.
  5. Move in. A Certificate of Occupancy closes it out.

Like-for-like: the 110% rule

Mayor Bass’s Emergency Executive Order No. 1, signed January 13, 2025, is the backbone of the rebuild. If you rebuild in substantially the same spot and stay within 110% of the old footprint and height, you skip discretionary review, CEQA, and Coastal Development Permits. The order also set a 30-day target for initial City reviews and lets displaced owners live in an RV, tiny home or modular unit on the lot while they rebuild.

You can add an ADU, a basement or new retaining walls and still count as like-for-like, according to City Planning’s Palisades Rebuild FAQ.

EO 8: going bigger near the coast

A lot of the Palisades sits in the Coastal Zone, where going bigger normally means a Coastal Commission process. Emergency Executive Order No. 8 (July 23, 2025) opened a second fast lane. Single-family rebuilds in the Coastal Zone can go beyond 110% and still skip Coastal review, as long as they meet today’s zoning, keep the same number of units (new ADUs excepted), and stay 10 feet from a canyon bluff or 25 feet from a coastal bluff.

Other City orders in the mix:

  • EO 7 (April 2025): suspended plan check and permit fees for fire-damaged single-family homes and duplexes.
  • EO 9: suspends SB 9 projects (up to four units on a single-family lot) in the burn area.
  • EO 10: fast-tracks commercial rebuilds in the Palisades Village.
  • Standard Plan Pilot (first approvals November 2025): pre-checked home designs owners can pick off the shelf.

Where it stands: by the numbers

Of the 1,357 new-home permits (single-family and duplex) tagged as fire rebuilds, 1,041 have passed at least one construction inspection. 798 have passed a framing inspection. 59 have a Certificate of Occupancy, and 5 more are in the CofO process.

The first one was 915 N Kagawa St, which got its CofO on November 21, 2025. Finishes are now picking up: 18 rebuilt homes got a CofO in October 2026 alone, the most of any month so far.

Plenty of homes are still at the starting line. 316 new-home permits haven’t passed a construction inspection yet.

Still climbing

The first rebuild permits trickled out in February and March 2025. By the end of 2025, the City had issued 1,338 fire rebuild permits in the area.

2026 is running at more than double that. January through October brought 2,993 permits, with a high of 350 in September and 343 in October. Unlike Altadena, where the monthly count has eased since the summer, the Palisades is still at or near its peak.

Those 4,331 permits carry $1.22 billion in declared value. The median new-home permit lists $600,000 in value and 3,530 square feet.

It’s not just houses

Counting original permits only (revisions excluded), the City has issued 1,013 grading permits for fire rebuilds, the second-biggest category after new homes. Hillsides, basements and re-compacted soil mean a lot of dirt moves before a stud goes up.

Then come 504 permits for retaining walls, fences and other site work, 207 for pools and spas, 207 for repairs and additions to homes that survived, and 172 for ADUs.

What it means if you work in the Palisades

  • Grading, concrete and foundations: 316 permitted homes haven’t passed a construction inspection yet, and new home permits are still coming at 60 to 100+ a month.
  • Framing, roofing, windows and MEP: 243 homes have started but haven’t passed framing yet, and 740 are past framing but not yet finished.
  • Finish trades and landscaping: 59 homes are done out of 1,357. The finish wave is just starting.
  • Pools, walls and hardscape: over 700 permits for pools, walls and site work so far.

BCAR DATA’s Los Angeles permit list is available at bcardata.com.

Method: “Fire rebuild” means the LADBS permit description tags the project as a 2025 wildfire or fire rebuild or cites the Mayor’s emergency orders, issued January 7, 2025 to October 30, 2026, in the Brentwood-Pacific Palisades Community Plan Area. Totals include supplemental (revision) permits; category and new-home counts use original permits only. Construction stages come from LADBS inspection records. Parts of the burn area in Malibu and unincorporated LA County are not included.